Out with the old…

Harris Park demoltion, faster than expected!Demolition on our Harris Park project went quicker than we anticipated.  The entire garage apartment structure was torn down and hauled off in just three days.  The rain came at just the wrong time, however, and digging out the old garage foundation was pushed as we waited for site to dry.  We moved our focus indoors to stay on schedule, and proceeded to demo most of the kitchen and the interior walls that needed to be removed.

The toughest part?  The old range.  It took five guys and a lift truck!  The owners had a wonderful vintage range and they were able to find a new home for it.

You can’t see it from these photos, but part of the demo involved removing an old chimney flue that ran up the center of the home.  Our demo team was able to save many of the chimney bricks, at the request of our owners, and they intend to use them in the landscaping once the project is finished.

Harris Park Project demolition